As part of the Transport for NSW ‘Permit/Plug/Play’ program, Council will shortly deliver upgrades to King Street Mall. These works are designed to reduce the cost and complexity of hosting street-based events with the goal of enhanced cultural, economic and social benefits.
Key Activities
When? | What? |
August | Early works – site investigations and setup of temporary work zones |
September | Earth works – trenching for new electrical and plumbing services |
Lights & power– install new fairy lights to trees and power outlets for future events equipment at both ends of the Mall | |
Plumbing – install new drinking fountain near Market St and playground | |
Safety barriers – install removable bollards near King Ln and low-height wall near Princes Hwy to prevent vehicle access | |
Paving – install new pavers to demarcate performance space adjacent new low-height wall and rectify all surfaces disturbed by above works | |
October | Works complete |