King Street Mall Rockdale

King Street Mall Works

Commencing soon

As part of the Transport for NSW ‘Permit/Plug/Play’ program, Council will shortly deliver upgrades to King Street Mall. These works are designed to reduce the cost and complexity of hosting street-based events with the goal of enhanced cultural, economic and social benefits. 

Start date
August
End date
October
Location
King Street Mall, Rockdale

Key Activities

When?

What?

August

Early works – site investigations and setup of temporary work zones

September 

Earth works – trenching for new electrical and plumbing services

Lights & power– install new fairy lights to trees and power outlets for future events equipment at both ends of the Mall

Plumbing – install new drinking fountain near Market St and playground

Safety barriers – install removable bollards near King Ln and low-height wall near Princes Hwy to prevent vehicle access

Paving – install new pavers to demarcate performance space adjacent new low-height wall and rectify all surfaces disturbed by above works

October

Works complete